Counters at grills create vertical stepholds that are less than 45 inches. Install mesh on fencing in those areas or other solid barrier. A couple of windows in the gym were missing the screws allowing the windows to be opened more than 4 inches. Screws were replaced.
4.0
General Comments
911 operator said that the line was 'a little staticky'. Look into replacing/repairing the phone.
VGB information verified. Items in compliance with VGB letter(s) on file at time of inspection.
0.0
11.
Two ladders loose and not completely flushed to the wall.
2.0
15.
Ring buoy rope too short at 45 feet. A minimum 1/4 inch diameter throwing rope as long as one and one-half times the maximum width of the pool or 50 feet, whichever is less, shall be attached to a U.S. Coast Guard approved ring buoy. New rope obtained and measured 50 feet. Permit issued.
Wake County Plan Review and Recreational Sanitation Section recommends pools be hyper chlorinated at least twice a month. This activity should be accurately logged on the CPO check list form.
No night swimming.
No imminent hazard found in pump room at time of inspection. Visible bonding wire attached and intact to pump. Have an electrician evaluate all the components to determine function, if not done so prior to permitting inspection. If an electrician finds a repair is needed, obtain an electrical permit from the appropriate municipality, and have the corrections inspected.
Wake County Plan Review and Recreational Sanitation Section recommends pools be hyper chlorinated at least twice a month. This activity should be accurately logged on the CPO check list form. Emergency phone does work, and 911 was able to confirm address & phone number. However, the phone is not listed as a pool phone. Please contact technician to confirm with 911 that this phone is for use at a pool.
Wake County Plan Review and Recreational Sanitation Section recommends pools be hyper chlorinated at least twice a month. This activity should be accurately logged on the CPO check list form.
This pool must remain closed until the local and state closure orders currently in effect as a result of the COVID-19 pandemic are terminated. 150 gpm pump appears to be properly grounded No night swimming.
Pool staff and patrons are strongly encouraged to comply with the most current CDC guidance concerning social distancing related to the COVID-19 pandemic.
Initial opening inspection. *Variable speed pump must be maintained at 140gpm during operation. *Windows from fitness room have screws installed to prevent opening >4".